2026 preventive maintenance plan
List
Calendar
Export CSV
Year
Jan
0/36
36
Feb
0/63
63
Mar
0/46
46
Apr
0/38
38
May
0/46
46
Jun
0/43
43
Jul
0/62
62
Aug
0/48
48
Sep
0/35
17
Oct
0/35
Nov
0/71
Dec
0/46
Plan
2026 plan (current)
2025 plan
2023 plan
2020 plan
2019 plan
Generating unit
All units
54G1
54G2
54G3
54G4
Station-wide
Category
All categories
Monthly
Quarterly (Unit)
Quarterly (Auxiliary)
Outside Services
Semi-annual (Auxiliary)
Annual
Level A
Status
Any status
Overdue
Not started
In progress
Completed
Search
Apply filters
48 tasks
in August 2026
48 overdue
Newest first
Oldest first
Monthly
Quarterly (Unit)
Quarterly (Auxiliary)
Outside Services
Semi-annual (Auxiliary)
Annual
Level A
Quarterly Maintenance on Utility Systems
0/2 done
Quarterly
1 day
Street Light Control Boxes #6,7,8,9,10
Aug 28 – Aug 29
EXPIRED
· 17d overdue
Not started
Street Light Control Boxes #1,2,3,4,5
Aug 28 – Aug 29
EXPIRED
· 17d overdue
Not started
Bi-annual Maintenance on Utility Systems
0/5 done
Semi-annual (Bi-annual)
1 day
50kVA Transformer @ Zenith Bank (JT03)
Aug 25
EXPIRED
· 20d overdue
Not started
50kVA Street Light Transformer 2 (JT02)
Aug 25
EXPIRED
· 20d overdue
Not started
Quarterly Maintenance on Power Transformer 54T5
EXPIRED
· 23d overdue
Not started
Quarterly
Aug 22
1 day
Semi-annual Maintenance on Cranes
0/1 done
Semi-annual (Bi-annual)
2 days
Intake Gantry Crane
Aug 21
EXPIRED
· 24d overdue
Not started
Quarterly Maintenance on Plant Auxiliaries
0/4 done
Quarterly
1 day
Dam Drainage Pump Motors/Panels
Aug 18
EXPIRED
· 27d overdue
Not started
Frequency Modulation Pump Motors/Panels
Aug 15 – Aug 19
EXPIRED
· 30d overdue
Not started
54G1 3rd Quarterly Mtce
54G1
0/11 done
Quarterly
1 day
Power Transformer 54T1
Aug 15
EXPIRED
· 30d overdue
Not started
Station Service Switchgears (1S Bus)
Aug 14
EXPIRED
· 31d overdue
Not started
54G1 3rd Quarterly Mtce
54G1
0/11 done
Quarterly
1 day
Power Transformer 54T1
Aug 15
EXPIRED
· 30d overdue
Not started
Station Service Switchgears (1S Bus)
Aug 14
EXPIRED
· 31d overdue
Not started
Monthly Battery Maintenance
0/10 done
Monthly
1 day
Emergency Diesel Generator Batteries @ Executive House
Aug 5
EXPIRED
· 40d overdue
Not started
Emergency Diesel Generator Batteries @ Turbinette
Aug 5
EXPIRED
· 40d overdue
Not started
Monthly Inspections on Units #1, #2 and #3 Cooling Water Switchgears
EXPIRED
· 44d overdue
Not started
Monthly
Aug 1
1 day
Monthly Inspections at the Switchyard
EXPIRED
· 44d overdue
Not started
Monthly
Aug 1
1 day
Monthly Inspections on Plant, Switchyard and Turbinette Lighting System
EXPIRED
· 44d overdue
Not started
Monthly
Aug 1
1 day
50kVA Street Light Transformer 1 (JT01)
Aug 25
EXPIRED
· 20d overdue
Not started
200kVA Transformer near Warehouse (F1T03)
Aug 24
EXPIRED
· 21d overdue
Not started
50kVA Transformer @ Y-junction (F1T02)
Aug 24
EXPIRED
· 21d overdue
Not started
Fire Pump Motors
Aug 15 – Aug 19
EXPIRED
· 30d overdue
Not started
SCO Compressor Motors/Panels
Aug 14 – Aug 18
EXPIRED
· 31d overdue
Not started
Unit 1 Aux. Power Panel
Aug 14
EXPIRED
· 31d overdue
Not started
Intake Hydraulic Gate Hoist Motors
Aug 13
EXPIRED
· 32d overdue
Not started
Oil Leakage Tank Motor
Aug 13
EXPIRED
· 32d overdue
Not started
Head Cover Pump Motors
Aug 13
EXPIRED
· 32d overdue
Not started
Dust Suction Pump Motors
Aug 12
EXPIRED
· 33d overdue
Not started
Governor Oil Pump Motors/Panels
Aug 12
EXPIRED
· 33d overdue
Not started
Collector Housing
Aug 11
EXPIRED
· 34d overdue
Not started
Excitation Panels
Aug 11
EXPIRED
· 34d overdue
Not started
Cooling Water Pump Motors/Control
Aug 8 – Aug 12
EXPIRED
· 37d overdue
Not started
Unit 1 Aux. Power Panel
Aug 14
EXPIRED
· 31d overdue
Not started
Intake Hydraulic Gate Hoist Motors
Aug 13
EXPIRED
· 32d overdue
Not started
Oil Leakage Tank Motor
Aug 13
EXPIRED
· 32d overdue
Not started
Head Cover Pump Motors
Aug 13
EXPIRED
· 32d overdue
Not started
Dust Suction Pump Motors
Aug 12
EXPIRED
· 33d overdue
Not started
Governor Oil Pump Motors/Panels
Aug 12
EXPIRED
· 33d overdue
Not started
Collector Housing
Aug 11
EXPIRED
· 34d overdue
Not started
Excitation Panels
Aug 11
EXPIRED
· 34d overdue
Not started
Cooling Water Pump Motors/Control
Aug 8 – Aug 12
EXPIRED
· 37d overdue
Not started
38AH Fire Alarm Batteries @ Turbinette
Aug 5
EXPIRED
· 40d overdue
Not started
200AH Communication Batteries @ Turbinette
Aug 5
EXPIRED
· 40d overdue
Not started
300AH Switchyard Batterries
Aug 5
EXPIRED
· 40d overdue
Not started
Forklift Batteries
Aug 4
EXPIRED
· 41d overdue
Not started
Emergency Diesel Generator Batteries @ Powerhouse
Aug 4 – Aug 8
EXPIRED
· 41d overdue
Not started
38AH Fire Alarm Batteries @ Powerhouse
Aug 4
EXPIRED
· 41d overdue
Not started
500AH Communication Batteries @ Powerhouse
Aug 4
EXPIRED
· 41d overdue
Not started
800AH Station Batteries
Aug 4
EXPIRED
· 41d overdue
Not started