Task group · 2025 plan
0 of 10 completed
No changes yet
Every edit made in the app is recorded here with who made it.
'Unit 1 Aux. Power Panel' refers to unit 1 but sits under '54G2 1st Quarterly Mtce'.
'Station Service Switchgears (1S Bus)' refers to unit 1 but sits under '54G2 1st Quarterly Mtce'.
'Power Transformer 54T1' refers to unit 1 but sits under '54G2 1st Quarterly Mtce'.
Planned finish read as 2025-01-13 (typo in date text).
Planned finish read as 2025-01-13 (typo in date text).
Planned finish read as 2025-01-14 (typo in date text).
Planned finish read as 2025-01-15 (typo in date text).
Planned start read as 2025-01-16 (typo in date text).
Planned finish read as 2025-01-16 (typo in date text).
Planned finish read as 2025-01-17 (typo in date text).
Same task in this and other years' plans