Task group · 2025 plan
0 of 22 completed
No changes yet
Every edit made in the app is recorded here with who made it.
'Power Transformer (54T3)' refers to unit 3 but sits under '54G1 Annual Mtce'.
'Unit 3 Auxiliary Power Panels' refers to unit 3 but sits under '54G1 Annual Mtce'.
'Station Service Switchgears(3S Bus)' refers to unit 3 but sits under '54G1 Annual Mtce'.
Annual group '54G1 Annual Mtce' appears 3 times in the 2025 plan (months 5, 7, 11).
Planned finish read as 2025-07-18 (typo in date text).
Planned finish read as 2025-07-22 (typo in date text).
Planned start read as 2025-07-24 (typo in date text).
Planned finish read as 2025-07-24 (typo in date text).
Planned start read as 2025-07-29 (typo in date text).
Same task in this and other years' plans